A profitable order can tie up cash in raw material, wages, subcontracting and inventory weeks before the customer pays. This worked example shows how to calculate the funding gap, negotiate better terms and decide where invoice discounting can help.
A manufacturer receives a ₹1 crore purchase order. The sales team estimates the order will leave ₹16 lakh after direct production and fulfilment costs, before financing and other overheads. The plant has enough machine capacity. The customer wants delivery in 45 days.
Then finance maps the payment dates. By dispatch, the factory will have spent ₹84 lakh. The customer’s payment is due 45 days after acceptance. The business has ₹70 lakh available for the order after protecting cash for existing commitments.
The order looks profitable. The factory is still ₹14 lakh short before it can finish the job.
That funding gap is the decision a CEO needs to see before approving the purchase order. Finding it after buying the material leaves the company with fewer options and less negotiating room.
What a ₹1 crore order looks like on a cash calendar
Consider an illustrative order for machined components. The customer pays no advance. The supplier dispatches the entire order on Day 45, the buyer accepts delivery that day and payment is due 45 days later. All amounts exclude GST. The cash schedule includes direct order outflows and assumes no interim receipts.
| Day | Cash event | Cash in or out | Cumulative order cash flow |
|---|---|---|---|
| Day 0 | Material advance and tooling deposit | −₹24 lakh | −₹24 lakh |
| Day 15 | Material balance and production setup | −₹12 lakh | −₹36 lakh |
| Day 30 | Machining, wages and outside processing | −₹26 lakh | −₹62 lakh |
| Day 45 | Remaining production costs, inspection, packing and freight | −₹22 lakh | −₹84 lakh |
| Day 90 | Customer pays the invoice | +₹1 crore | +₹16 lakh |
The numbers answer three different questions.
- How much does the order leave after the listed costs? ₹16 lakh before financing, tax and any additional overhead or warranty costs.
- How much cash is tied up at the lowest point? ₹84 lakh from Day 45 until payment arrives, under the assumptions above.
- How much extra funding does the factory need? ₹14 lakh if only ₹70 lakh is available for this order. The shortage appears by Day 45.
Use this calculation to review any large order. Find the lowest cumulative cash balance on the order calendar, then compare the amount needed with the cash and credit the business can actually use on that date.
Why a profitable factory can run short of cash
An order moves through three stages that consume cash. The factory buys material and pays to convert it. Finished goods may then wait for inspection or dispatch. Once goods are delivered, the factory carries the receivable until payment arrives.
A factory can estimate this cycle using inventory days + receivable days − payable days. That measure helps track the business over time. For a large or unusual order, build a dated cash forecast as well. An average can hide a material advance, a tooling deposit or a delayed inspection that creates a shortage in a particular week.
Start with cash and genuinely drawable credit. Deduct the amounts already needed for payroll, taxes, debt service, critical suppliers and existing orders. Then run the new order through a rolling 13-week cash forecast, extending the forecast if final payment falls later. This shows whether the business can finance the new work while keeping existing deliveries on schedule.
Find out what starts the payment clock
A purchase order may say “45 days.” Before accepting it, find out which event establishes the due date and who records that event.
Ask the buyer’s purchasing and accounts teams to walk through a previous invoice for the same type of supply.
| Question to ask | What the answer tells you |
|---|---|
| Who records receipt and completes inspection? | Which team can confirm that delivery has been accepted |
| Which documents must accompany each invoice? | Whether a missing inspection report, goods receipt or portal entry can stall processing |
| Can individual lots be accepted and invoiced? | Whether earlier dispatches can generate earlier receipts |
| How are partial rejections or quantity disputes handled? | Whether the buyer can process the accepted quantity while the disputed items are resolved |
| On which date would a sample invoice actually be paid? | How the buyer’s payment process affects your cash forecast |
For eligible micro and small enterprise suppliers, Section 15 of the MSMED Act caps a written payment agreement at 45 days from acceptance or deemed acceptance. Where there is no written agreement, payment is due before the statutory appointed day. The Act defines that day and explains how a timely written objection affects acceptance. Keep delivery acknowledgements, inspection records and written correspondence together so the team can establish what happened if a payment is delayed. Eligible suppliers can also use the Ministry of MSME’s Samadhaan route for delayed-payment disputes. MSMED Act, Sections 2 and 15 · Ministry of MSME — Samadhaan. msmediagra.gov.in
A cash forecast can still model a late receipt. If payment slips from Day 90 to Day 105 in this example, the ₹84 lakh peak stays the same, but the factory carries it for 15 additional days. If the full ₹84 lakh were financed at an illustrative annual rate of 14%, those extra days would cost approximately ₹48,300 in simple interest. The actual cost depends on how much the business borrows and for how long.
What TReDS can do for a manufacturing MSME
The Reserve Bank of India issued its revised Trade Receivables Discounting System (TReDS) Directions on 23 June 2026, effective immediately. The directions simplify MSME seller onboarding and allow financiers to use eligible credit guarantee cover for exposures on the platform. TReDS enables participating MSMEs to receive funds against accepted receivables through bids from financiers. Source — RBI’s TReDS Directions, 2026. rbi.org.in
Here is how a transaction can work. An invoice or bill is uploaded and the buyer accepts the factoring unit on the platform. Financiers bid to discount it. If a bid is accepted and the transaction settles, the seller receives the discounted amount and the buyer pays the financier on the due date. Under the RBI directions, discounted factoring units are without recourse to the seller for buyer default. The directions also require a seller declaration addressing existing financing or charges on the underlying goods or services. Check that declaration with your working capital bank and the platform before relying on the facility. Source — RBI’s TReDS Directions, Chapter III. rbi.org.in
The timing matters more than the headline rate
Suppose the ₹1 crore order is split into separately invoiced lots at dispatch, and an invoice for ₹60 lakh is accepted and discounted on Day 55. Payment is due on Day 90. At an illustrative annualised discount rate of 12.5% for 35 days, the discount would be about ₹71,900, leaving approximately ₹59.28 lakh in early proceeds before platform fees and applicable taxes.
That brings cash into the factory 35 days earlier. The plant still needs funding for its Day 45 peak because the discounted proceeds arrive on Day 55. The CEO must secure the pre-dispatch funding separately and confirm when the buyer can accept the invoice, whether the buyer participates on the platform, and what the actual bid and charges are.
What to negotiate before signing the purchase order
The best time to address the ₹14 lakh shortage is while the buyer and supplier are agreeing on how the work will be funded and delivered.
| What to negotiate | How it changes the cash requirement |
|---|---|
| ₹20 lakh advance against material | If received before purchasing starts, it reduces the example’s pre-collection peak from ₹84 lakh to ₹64 lakh. The ₹70 lakh available then covers the order with a ₹6 lakh buffer, before contingencies. |
| Separate tooling milestone | A tooling payment when the tool is completed or approved brings in cash before serial production invoices are due. |
| Firm releases in smaller lots | Staging procurement and production can spread outlays. If the buyer also accepts and pays each lot separately, receipts can begin earlier. |
| Defined acceptance process | A named approver, clear inspection criteria and a complete document list make it easier to forecast invoice timing and resolve exceptions. |
| Supplier credit aligned to the production schedule | Later material payments reduce the amount the factory must fund upfront. Compare the supplier’s terms with any price increase or discount forgone. |
| TReDS or another agreed receivables facility | Earlier collection on an accepted invoice can release cash for the next production cycle. Include discount costs and fees in the quotation. |
A practical discussion with the buyer can be simple.
We can meet the delivery schedule. The order requires dedicated material and tooling upfront. A 20% material advance or a separate tooling milestone would let us reserve that capacity and commit to the agreed dates.
Put the agreed terms into the purchase order or related commercial documents so production and finance can plan around the same dates.
The questions every CEO should ask before approving a large order
Bring sales, production, procurement and finance into the same review. Ask each team to put dates and amounts against its assumptions.
- What does the order earn after all incremental costs? Include yield losses, rework, outside processing, tooling, testing, freight and financing. Recalculate the margin at the actual quantities the customer is committing to buy.
- When is the cash balance lowest? List each major outflow and receipt by date. Include GST, duties and deposits where they affect cash timing.
- How much can we draw in that week? Use available cash and confirmed borrowing headroom after existing commitments. Check any borrowing-base or drawdown conditions with the lender.
- What happens if acceptance or payment slips by 15 days? Run the delay through the whole business forecast. Check which existing deliveries, supplier payments or payroll dates come under pressure.
- Which term would make the order viable? Ask whether an advance, tooling milestone, staged releases or a confirmed financing line closes the gap. Assign one person to verify that term before procurement commits the cash.
For the ₹1 crore order in this example, a ₹20 lakh advance makes the cash plan feasible under the stated assumptions. Invoice discounting on Day 55 helps fund what comes next. The difference is timing. One brings cash in before the factory reaches its peak outflow, and the other releases cash after the buyer accepts an invoice. That distinction can determine whether the plant delivers the new order without disrupting the rest of its business.